This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Please note, we have restricted the night work as follows in the permit. “You are hereby permitted to commence work at 1:00AM on Monday, August 18, 2014 on Thayer St. from Waterman St. to Cushing St. only. Work on Thayer St. from Cushing St. to Bowen St. will not be performed until after 7:00AM due to the higher concentration of residential dwellings. We also request that paving operations begin at Waterman St. and progress toward Bowen St. to minimize the noise in the residential area during overnight hours. Idling trucks shall be restricted to Thayer St. (Waterman St. to Cushing St.) and not be present on the residential side streets connecting to Thayer St. during the 1 AM to 7 AM time period.” We are trying to limit impacts to all parties and ask for your continued patience. Monday night will complete construction work at the night in the area with the exception of the placement of pavement markings which will have minimal noise impact. Construction Update ********************************************************************* Parking Restrictions: NO PARKING Please note the following parking restriction will be in place start tomorrow- August 16th
1. Bituminous pavement will be placed on the following streets starting 7-18-14.
2. College Hill will resurfaced on Saturday 8-23-14. 3. Curb, sidewalk, and wheelchair ramp repairs will start/continue on Hope Street from Waterman Avenue to Wickenden Street, Star Street, and Church Street from 8-18-14 to 8-22-14. 4. The existing bituminous surface on Church Street will be removed and graded on 8-25-14 and 8-26-14. The roadway will be resurfaced on 8-29-14 5. The existing bituminous surface on Star Street will be removed and graded on 8-27-14 and 8-28-14. The roadway will be resurfaced on 8-29-14 6. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 7. Providence Water continues to perform repair work (various areas) throughout the East Side. Comments are closed.
|
Thayer Street
|