Thayer Street, Providence, RI: The Thayer Street District Management Authority announces 1st Annual Thayer Street Holiday Stroll.on December 14th 12 am to 4 pm. Thayer Street will host Santa and his elves, Olde Towne Carolers, Brown Student Carolers, LIVE music and special discounts at many of the businesses up and down the street.
Thayer Street, Providence, RI: Thayer Street District Management Authority reports their 1st Annual Thayer Fall Artisan Festival September 20th on Thayer Street in College Hill to be a success with over 2000+ in attendance. TSDMA Board member officially open the Thayer Parklet during the event. The TSDMA plans to make with festival an yearly event.
This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Please note, we have restricted the night work as follows in the permit. “You are hereby permitted to commence work at 1:00AM on Monday, August 18, 2014 on Thayer St. from Waterman St. to Cushing St. only. Work on Thayer St. from Cushing St. to Bowen St. will not be performed until after 7:00AM due to the higher concentration of residential dwellings. We also request that paving operations begin at Waterman St. and progress toward Bowen St. to minimize the noise in the residential area during overnight hours. Idling trucks shall be restricted to Thayer St. (Waterman St. to Cushing St.) and not be present on the residential side streets connecting to Thayer St. during the 1 AM to 7 AM time period.” We are trying to limit impacts to all parties and ask for your continued patience. Monday night will complete construction work at the night in the area with the exception of the placement of pavement markings which will have minimal noise impact. Construction Update ********************************************************************* Parking Restrictions: NO PARKING Please note the following parking restriction will be in place start tomorrow- August 16th
1. Bituminous pavement will be placed on the following streets starting 7-18-14.
2. College Hill will resurfaced on Saturday 8-23-14. 3. Curb, sidewalk, and wheelchair ramp repairs will start/continue on Hope Street from Waterman Avenue to Wickenden Street, Star Street, and Church Street from 8-18-14 to 8-22-14. 4. The existing bituminous surface on Church Street will be removed and graded on 8-25-14 and 8-26-14. The roadway will be resurfaced on 8-29-14 5. The existing bituminous surface on Star Street will be removed and graded on 8-27-14 and 8-28-14. The roadway will be resurfaced on 8-29-14 6. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 7. Providence Water continues to perform repair work (various areas) throughout the East Side.
Meet the other four finalists: Michele Costantino from South Bend, IN; Olivia Watson from Providence, RI (a student Brown University student); John Gosselin from Warwick, RI; and Branko Skendzic from Zagreb, Croatia.
This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed tomorrow and Friday on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement. Brook Street - Cushing Street to Hope Street - Friday 7:00 am to 4:30 pm Thayer Street - Bowen Street to Hope Street - Thursday 7:00 am to Noon Meeting Street - Thayer Street to Prospect Street - Thursday 7:00 am to 4:30 pm Hope Street - Waterman Street to Cushing Street - Friday 7:00 am to 4:30 pm Meeting Street - Hope Street to Brook Street - Friday 7:00 am to 4:30 pm Brook Street – Angell Street to Hope Street (excluding Meeting Street to Euclid Street) Friday 7:00 am to 4:30 pm 2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured this week. 3. Parking Restrictions “No Parking” will be as follows to perform the above. Thayer Street - Bowen Street to Hope Street - Thursday 7 am to 5 pm Thayer Street - Waterman Street to Cushing Street – Thursday 1 am to 12 noon (night work) Hope Street - Waterman Street to Cushing Street – Thursday & Friday 7 am to 5 pm Brook Street - Angell Street to Hope Street – Thursday & Friday 7 am to 5 pm Meeting Street - Thayer Street to Prospect Street – Thursday & Friday 7 am to 5 pm 4. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed next week (week of August 11) on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement.
2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured. 3. Parking Restrictions “No Parking” will be as follows to perform the above.
4. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed next week on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement.
2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured. 3. Parking Restrictions “No Parking” will be as follows to perform the above.
5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. Repair will be performed this Saturday (8/2/14) 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows:Construction Update: 1. There will be no placement of bituminous pavement next week. 2. Minor construction work will continue next weeks with no road closures by Contract No. 8 · Adjusting utility frames and covers · Curb and driveway apron repair and replacement. · Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). 3. Parking Restrictions “No Parking” will be as follows to perform Items 1 and 2 above. · College Street - North Main to Prospect – 7/26/14, Saturday 7am to 5pm. · Thayer Street - John to George -7/28/14 & 7/29/14, Monday & Tuesday - 7am to 5pm · Hope Street - Waterman to Cushing – 7/29/14 & 7/30/14, Tuesday & Wednesday - 7am to 5pm This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Placement of Bituminous Pavement (This is the first layer of bituminous pavement to be placed): (Road Closures & No Parking) · Meeting Street (Thayer Street to Prospect Street) FRIDAY 7-17-14 from 7:00 A.M. to 4:00 P.M. (Rescheduled due to rain) · Lloyd Avenue (Prospect Street to Brook Street) FRIDAY 7-17-14 from 7:00 A.M. to 4:00 P.M. 2. Minor construction work will continue over the next few weeks and includes the following: (No Road Closures) · Adjusting utility frames and covers · Curb repair and replacement. 3. Parking Restrictions “No Parking” will be as follows to perform Items 1 and 2 above. · Thayer Street – Bowen to Hope – Friday 18th & Monday 21st (7am to 5pm) · Thayer Street – John to George – Friday 18th and all of next week Monday 21st to Friday 25th (7am to 5pm) · Meeting Street – Prospect to Thayer – Friday 18th to Tuesday 22nd (excludes the weekend) (7am to 5pm) · Lloyd Avenue – Prospect to Hope – Friday 18th & Wednesday 23rd to Friday 25th (7am to 5pm) · College Street – North Main to Prospect – Saturday 19th (7am to 5pm) 4. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). This work will consist of providing curb modifications, “bump-outs”, to provided additional sidewalk area, benches, and landscaping. The work has been re-scheduled to start July 18, 2014. (No Road Closures) |