Thayer Street Announces Completion of District Wide Tree Well & Sidewalk Improvement Project9/18/2015
The Thayer Street District Management Authority (TSDMA) announces the completion of a district wide tree well & sidewalk improvement project in time for the Thayer Fall Artisan Festival. Dangerous sidewalks were removed and replaced with new level concrete. Tree wells were re-sized by block and lined with cobblestones to enhance the visual appeal of the district as well as to provide addition protection for the District's trees. In addition, three new trees were planted to replace damaged trees that had been removed years earlier. A bicycle repair station was also installed as part of this project on the Olive Street side of the Brown Bookstore. The total cost of the District Improvement Project was approx. $35,000. and fully funded by the Thayer Street District Management Authority.
This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Please note, we have restricted the night work as follows in the permit. “You are hereby permitted to commence work at 1:00AM on Monday, August 18, 2014 on Thayer St. from Waterman St. to Cushing St. only. Work on Thayer St. from Cushing St. to Bowen St. will not be performed until after 7:00AM due to the higher concentration of residential dwellings. We also request that paving operations begin at Waterman St. and progress toward Bowen St. to minimize the noise in the residential area during overnight hours. Idling trucks shall be restricted to Thayer St. (Waterman St. to Cushing St.) and not be present on the residential side streets connecting to Thayer St. during the 1 AM to 7 AM time period.” We are trying to limit impacts to all parties and ask for your continued patience. Monday night will complete construction work at the night in the area with the exception of the placement of pavement markings which will have minimal noise impact. Construction Update ********************************************************************* Parking Restrictions: NO PARKING Please note the following parking restriction will be in place start tomorrow- August 16th
1. Bituminous pavement will be placed on the following streets starting 7-18-14.
2. College Hill will resurfaced on Saturday 8-23-14. 3. Curb, sidewalk, and wheelchair ramp repairs will start/continue on Hope Street from Waterman Avenue to Wickenden Street, Star Street, and Church Street from 8-18-14 to 8-22-14. 4. The existing bituminous surface on Church Street will be removed and graded on 8-25-14 and 8-26-14. The roadway will be resurfaced on 8-29-14 5. The existing bituminous surface on Star Street will be removed and graded on 8-27-14 and 8-28-14. The roadway will be resurfaced on 8-29-14 6. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 7. Providence Water continues to perform repair work (various areas) throughout the East Side. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed tomorrow and Friday on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement. Brook Street - Cushing Street to Hope Street - Friday 7:00 am to 4:30 pm Thayer Street - Bowen Street to Hope Street - Thursday 7:00 am to Noon Meeting Street - Thayer Street to Prospect Street - Thursday 7:00 am to 4:30 pm Hope Street - Waterman Street to Cushing Street - Friday 7:00 am to 4:30 pm Meeting Street - Hope Street to Brook Street - Friday 7:00 am to 4:30 pm Brook Street – Angell Street to Hope Street (excluding Meeting Street to Euclid Street) Friday 7:00 am to 4:30 pm 2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured this week. 3. Parking Restrictions “No Parking” will be as follows to perform the above. Thayer Street - Bowen Street to Hope Street - Thursday 7 am to 5 pm Thayer Street - Waterman Street to Cushing Street – Thursday 1 am to 12 noon (night work) Hope Street - Waterman Street to Cushing Street – Thursday & Friday 7 am to 5 pm Brook Street - Angell Street to Hope Street – Thursday & Friday 7 am to 5 pm Meeting Street - Thayer Street to Prospect Street – Thursday & Friday 7 am to 5 pm 4. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed next week (week of August 11) on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement.
2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured. 3. Parking Restrictions “No Parking” will be as follows to perform the above.
4. National Grid continues to perform repair work throughout the area. We would note work is scheduled on Meeting Street, Euclid Street, and Brook Street within the block area of 257 Thayer Street. 5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Bituminous pavement will be placed next week on the following streets. Please note, construction crews will be working on these streets the days prior to the placement of bituminous pavement.
2. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). Sidewalks will be poured. 3. Parking Restrictions “No Parking” will be as follows to perform the above.
5. Providence Water continues to perform repair work (various areas) throughout the East Side. 6. Final pavement on College Hill has been delayed to allow for additional sidewalk and wheelchair repairs. Repair will be performed this Saturday (8/2/14) 7. Curb and sidewalk repairs will begin on Hope Street from Waterman Avenue to Wickenden Street. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows:Construction Update: 1. There will be no placement of bituminous pavement next week. 2. Minor construction work will continue next weeks with no road closures by Contract No. 8 · Adjusting utility frames and covers · Curb and driveway apron repair and replacement. · Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). 3. Parking Restrictions “No Parking” will be as follows to perform Items 1 and 2 above. · College Street - North Main to Prospect – 7/26/14, Saturday 7am to 5pm. · Thayer Street - John to George -7/28/14 & 7/29/14, Monday & Tuesday - 7am to 5pm · Hope Street - Waterman to Cushing – 7/29/14 & 7/30/14, Tuesday & Wednesday - 7am to 5pm This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Placement of Bituminous Pavement (This is the first layer of bituminous pavement to be placed): (Road Closures & No Parking) · Meeting Street (Thayer Street to Prospect Street) FRIDAY 7-17-14 from 7:00 A.M. to 4:00 P.M. (Rescheduled due to rain) · Lloyd Avenue (Prospect Street to Brook Street) FRIDAY 7-17-14 from 7:00 A.M. to 4:00 P.M. 2. Minor construction work will continue over the next few weeks and includes the following: (No Road Closures) · Adjusting utility frames and covers · Curb repair and replacement. 3. Parking Restrictions “No Parking” will be as follows to perform Items 1 and 2 above. · Thayer Street – Bowen to Hope – Friday 18th & Monday 21st (7am to 5pm) · Thayer Street – John to George – Friday 18th and all of next week Monday 21st to Friday 25th (7am to 5pm) · Meeting Street – Prospect to Thayer – Friday 18th to Tuesday 22nd (excludes the weekend) (7am to 5pm) · Lloyd Avenue – Prospect to Hope – Friday 18th & Wednesday 23rd to Friday 25th (7am to 5pm) · College Street – North Main to Prospect – Saturday 19th (7am to 5pm) 4. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). This work will consist of providing curb modifications, “bump-outs”, to provided additional sidewalk area, benches, and landscaping. The work has been re-scheduled to start July 18, 2014. (No Road Closures) This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Placement of Bituminous Pavement (This is the first layer of bituminous pavement to be placed): (Road Closures & No Parking) · Meeting Street (Thayer Street to Prospect Street) FRIDAY 7-17-14 from 7:00 A.M. to 4:00 P.M. (Rescheduled due to rain) 2. Minor construction work will continue over the next few weeks and includes the following: (No Road Closures) · Adjusting utility frames and covers · Curb repair and replacement. 3. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). This work will consist of providing curb modifications, “bump-outs”, to provided additional sidewalk area, benches, and landscaping. The work has been re-scheduled to start July 16, 2014. (No Road Closures) 4. Special 257 Thayer Construction Site Update: Concrete pour at 257 Thayer Site will be Thursday 7-17-14 from 6:30 am to 3:30. This will make Euclid, Brook, and Meeting one way traffic during this time period. This information is provided by the Thayer Street District Management Authority with approval from Todd Ravenell Project Manager (Consultant for the City of Providence) of Gordon R. Archibald, Inc., Civil and Environmental Engineers. Any reprint or social media re-post should include these credits and the URL of this post for authenticity.
The following is an updated summary of the roadway improvements proposed within the area of the Thayer Street and Brown University. The tentative schedule (weather dependent) is as follows: Construction Update: 1. Placement of Bituminous Pavement (This is the first layer of bituminous pavement to be placed): (Road Closures & No Parking) · Meeting Street (Thayer Street to Prospect Street) Wednesday 7-16-14 from 7:00 A.M. to 4:00 P.M. (Rescheduled due to rain) 2. Minor construction work will continue over the next few weeks and includes the following: (No Road Closures) · Adjusting utility frames and covers · Curb repair and replacement. 3. Thayer Street Improvements at the intersections of Cushing Street (Corner of No. 271) and at the intersection of Meeting Street (Corners of Nos. 288-296 & No. 300). This work will consist of providing curb modifications, “bump-outs”, to provided additional sidewalk area, benches, and landscaping. The work has been re-scheduled to start July 16, 2014. (No Road Closures) SPECIAL 257 Thayer Street CONSTRUCTION NOTICE (Rescheduled due rain to Thursday, July 17: This will effect the Thayer Street Area - the TSDMA was just notified by Gilbane Construction that they will be pouring 300 yards of concrete at their 257 Thayer construction site Thursday 7-17-14. This work on their site will cause Meeting Street, Euclid Street and Brook Street to become one lane starting 6:00am until approx 6pm. Thayer Street Businesses will be open. |
Thayer Street
|